This premises was found to be in compliance with the Health Protection and Promotion Act R.S.O. 1990.
This premises was found to be in compliance with the Health Protection and Promotion Act R.S.O. 1990.
Corrected During Inspection
Critical
Safety equipment required for operation as a public pool provided.
This premises was found to be in compliance with the Health Protection and Promotion Act R.S.O. 1990.
Not in Compliance
Non-critical
Facility completes and records daily tests at least 30 minutes prior to opening and as required.
Not in Compliance
Critical
Facility maintains pH level as required.
- Maintain pH value within the range of 7.2 to 7.8
- Enforcement action taken.
Not in Compliance
Non-critical
Facility completes daily records as required.
Not in Compliance
Critical
Facility maintains disinfectant level as required.
- Pool - Ensure residual of free available chlorine of public pool water maintained between 0.5 - 10 ppm.
- Enforcement action taken.
Not in Compliance
Non-critical
Facility maintains total alkalinity level as required.
- Maintain total alkalinity in the range of 80 ppm to 120 ppm.
Not in Compliance
Non-critical
Water meter & make-up water requirements are met.
- Ensure make-up water is added to the pool during each operating day in a minimum amount of 15 litres per bather.
This premises was found to be in compliance with the Health Protection and Promotion Act R.S.O. 1990.
This premises was found to be in compliance with the Health Protection and Promotion Act R.S.O. 1990.
Not in Compliance
Non-critical
Facility completes daily records as required.
- Record the reading of the make-up water meter for pools and, if applicable, for spas, as of the end of the day.
Not in Compliance
Critical
Facility operational requirements met
Not in Compliance
Non-critical
Facility completes weekly or monthly tests as required.
- Test-buttons associated with the ground current leakage detecting and de-energizing devices are activated daily, and tested either monthly or in accordance with manufacturer's directions, whichever is more frequent.
- Emergency stop button is labelled, and tested, and recorded once within each period of 30 operating days.